Client : ERICSSON
End User: OMV
Location : Lac, Tunis-Tunisia

Scope of Work:

  • Factory Acceptance Test (FAT):
    • Objective: To ensure that the security and telecommunication systems meet the specified requirements and standards before they are installed on-site.
    • Procedure:
      • Define the acceptance criteria based on OMV standards and Ericsson’s technical solution.
      • Prepare a test plan that outlines the specific tests to be conducted.
      • Assemble the necessary equipment and personnel for testing.
      • Perform functional and performance testing of each system component.
      • Document test results and discrepancies.
      • Generate a FAT report with pass/fail results and recommendations for addressing any issues.
  • Precommissioning & Commissioning
    • Elaboration of Precommissioning Procedure
    • Elaboration of Commissioning Procedure
  • Operator Manual:
    • Objective: To provide operators with comprehensive documentation for the security and telecommunication systems.
    • Procedure:
      • Compile detailed operating instructions for each system component.
      • Include troubleshooting guides and maintenance procedures.
      • Provide system schematics, network diagrams, and component specifications.
      • Ensure that the manual is user-friendly and easily accessible.
      • Review the manual with operators and incorporate their feedback.
      • Distribute the final manual to all relevant personnel and maintain version control.